Temporary funding delays seasonal shutdown at UMTRA site
by Rudy Herndon
Staff Writer
Nov 07, 2013 | 971 views | 0 0 comments | 40 40 recommendations | email to a friend | print
Cleanup work at the Moab Uranium Mill Tailings Remedial Action (UMTRA) Project will continue with few interruptions — through the middle of next January, at least.

The project had been scheduled to temporarily shut down beginning in November, according to Grand County UMTRA Liaison Lee Shenton. But on Oct. 21, the U.S. Department of Energy (DOE) informed the 136 employees currently working at the site that the agency received an internal allocation to fund the project through Jan. 15, Shenton said.

“I talked to a couple of the employees, and they’re breathing a sigh of relief that they’re going to have most of their work through December,” he told the Moab Tailings Project Steering Committee on Oct. 22.

Under the funding deal, the DOE plans to schedule eight work curtailment days between late October and January.

No firm dates have been mentioned at this point, Shenton said, but the DOE will likely schedule the breaks around the upcoming holidays.

“Then they’re all up in the air again after Jan. 15 rolls around,” he said.

The Jan. 15 date is not an arbitrary one.

Congress reached a deal on Oct. 16 to end the federal government shutdown. But the stopgap measure it approved will only fund the government through mid-January.

“We are thankful the short-term funding measure enacted by Congress provides funding to continue moving tailings at least through mid-January,” Federal Project Director Donald Metzler told The Times-Independent.

Overall work at the UMTRA Project could wrap up by 2025. However, the pace of progress will depend on funding commitments from the federal government.

The first rail shipments from the project site to a disposal cell near Crescent Junction began in 2009, thanks to a boost of federal stimulus money.

As of August 2013, crews had removed 6.2 million tons of mill tailings. That accounts for a 39 percent drop from the 16 million tons entombed at the site when the Atlas uranium processing mill closed in 1984.

Portage, Inc., is the lead contractor on the project. The DOE awarded a $121 million contract to the Idaho Falls, Idaho-based company in late-2011.

Copyright 2013 The Times-Independent. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

report abuse...

Express yourself:

We're glad to give readers a forum to express their points of view on issues important to this community. That forum is the “Letters to the Editor.” Letters to the editor may be submitted directly to The Times-Independent through this link and will be published in the print edition of the newspaper. All letters must be the original work of the letter writer – form letters will not be accepted. All letters must include the actual first and last name of the letter writer, the writer’s address, city and state and telephone number. Anonymous letters will not be accepted.

Letters may not exceed 400 words in length, must be regarding issues of general interest to the community, and may not include personal attacks, offensive language, ethnic or racial slurs, or attacks on personal or religious beliefs. Letters should focus on a single issue. Letters that proselytize or focus on theological debates will not be published. During political campaigns, The Times-Independent will not publish letters supporting or opposing any local candidate. Thank you letters are generally not accepted for publication unless the letter has a public purpose. Thank you letters dealing with private matters that compliment or complain about a business or individual will not be published. Nor will letters listing the names of individuals and/or businesses that supported a cause or event. Thank you letters about good Samaritan acts will be considered at the discretion of the newspaper.