During the second public open house on June 27, the Utah Department of Transportation answered questions and received more public comments about their plan to widen North Main Street. The project will expand North Main Street, a section of U.S. Highway 191, to four lanes with a center two-way left turn lane in the center where possible. It aims to reduce traffic congestion by eliminating the bottlenecks where two lanes merge into one. The project ranges from the intersection at 400 North—where the road narrows in front of the Hampton Inn—to the junction with Scenic Route 128 at the Colorado River bridge.

UDOT Project Manager Troy Torgersen said the design process is at about 50 percent. They plan to begin construction sometime between late fall 2018 and early winter 2019. With that timeframe, they expect to complete the project in the fall of 2019.

After the first open house in February, some changes to the plan were made. According to Kevin Kitchen, the UDOT region four communications manager, the most significant alteration was the addition of a sidewalk on the west side of the road. Other updates include putting in a crosswalk beneath the stop light at the SR-128 junction and extending the paved bike path from Lions Park to a point near the Moab Rock Shop. They also added an access point on the west side of the road across from the new terminus of the bike path, so the city can eventually connect 100 West or the Mill Creek Parkway to the north side of Main Street.

Kitchen said attendance at the second open house was lower than at the first, but they still received a variety of comments, both positive and negative. Kitchen claimed a couple local business owners expressed concerns over the elimination of on-street parking in the plan. With the roadway expanded to four lanes, plus a turning lane and a six-foot shoulder that leaves room for bikes, there was no longer any room for parking. Kitchen noted UDOT is pleased that they “won’t have to remove any buildings” to widen the road.

Kitchen said they received several positive comments about the addition of a sidewalk on the road’s west side. Many people were wondering how the project would impact pedestrians crossing the highway. Currently, the plan has crosswalks at the stoplights at 500 West and SR-128. Torgersen said crosswalks at 400 North and the new access point are also being considered but may be left up to the city. There were also questions about how the new crossing at SR-128 will affect signal timing, but that answer is still uncertain.

Another topic repeatedly brought up by residents was the question of speed limits in the project area. No decision has been made yet, but Kitchen said UDOT “will conduct a traffic study to determine if the speed limit should be lowered.”

Some people asked what hours of the day the construction will take place. “This project’s specifications are not to that level of detail yet,” said Kitchen. “Specific days and hours are usually determined by the contractor after the bid is awarded.”

A major part of the project will be the construction of a storm drainage system that will convey run-off from Stewart Canyon, the highway and adjacent areas to a retention pond located west of the intersection of 500 West and Highway 191. The system is designed to handle flooding from a 50-year storm event.

UDOT has a third public open house tentatively planned for late August or early September. The focus of the next open house will be discussing the environmental assessment of the plan.


Copyright 2013 The Times-Independent. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

report abuse...

Express yourself:

We're glad to give readers a forum to express their points of view on issues important to this community. That forum is the “Letters to the Editor.” Letters to the editor may be submitted directly to The Times-Independent through this link and will be published in the print edition of the newspaper. All letters must be the original work of the letter writer – form letters will not be accepted. All letters must include the actual first and last name of the letter writer, the writer’s address, city and state and telephone number. Anonymous letters will not be accepted.

Letters may not exceed 400 words in length, must be regarding issues of general interest to the community, and may not include personal attacks, offensive language, ethnic or racial slurs, or attacks on personal or religious beliefs. Letters should focus on a single issue. Letters that proselytize or focus on theological debates will not be published. During political campaigns, The Times-Independent will not publish letters supporting or opposing any local candidate. Thank you letters are generally not accepted for publication unless the letter has a public purpose. Thank you letters dealing with private matters that compliment or complain about a business or individual will not be published. Nor will letters listing the names of individuals and/or businesses that supported a cause or event. Thank you letters about good Samaritan acts will be considered at the discretion of the newspaper.