Project aims to increase water pressure in Spanish Valley
by Zenaida Sengo
The Times-Independent
Jan 10, 2019 | 671 views | 0 0 comments | 10 10 recommendations | email to a friend | print
Trinity construction crew lays a new 8-inch waterline in front of Spanish Trail Arena.      Photo by Zenaida Sengo
Trinity construction crew lays a new 8-inch waterline in front of Spanish Trail Arena. Photo by Zenaida Sengo
slideshow


The project to increase Spanish Valley’s culinary water pressure and fire flow capacity has commenced and excavations to the system will cause upcoming, partial-day water shutoffs in upcoming weeks.

Grand Water Sewer and Service Agency Manager Dana Van Horn said those involved in the project have been working to make sure all preliminary work that can be done prior to construction is completed before excavation in order to minimize the length of disruption. Roads are expected to remain passable with traffic diverted around the construction. Temporary water shutoffs are expected to last a few hours and those affected will receive 48-hour notice.

The new upgrades to the system have been outlined in GWSSA’s culinary water master plan since 2016, and include wider-diameter waterlines to accommodate flow increase, an increase in hydrant quantity, and the addition of a large new tank.

The area’s peak day instantaneous demand, which generally equates to midday midsummer water usage, is projected to increase by nearly 50 percent over the next 20 years. This will result in a strain on firefighting capacity.

The standard fire flow increased from 1000 gallons per minute to 1,500 GPM. Van Horn said that while the flow isn’t detrimentally low in the system’s present state, the increase in hydrant quantity and flow will better accommodate an emergency situation where maximum flow from every hydrant is needed, as in the Cinema Court Fire last summer when eight homes burned.

Van Horn said when the agency disabled a pressure-reducing valve for firefighters in June, some areas of the system were over-pressurized, and one resident’s water heater was damaged. GWSSA paid for the resident’s repair. Van Horn said that some system complications are expected when a fire is that massive. “It was minor damage, nothing compared to the devastation of the fire, and hopefully that one water heater saved at least one person’s home.”

Distance between hydrants in the fire area will decrease to approximately 500 feet with a couple of new additions along Murphy Lane. Exact locations are expected near Mill Creek Drive’s intersections with Murphy Lane and Arbor Drive, but are subject to change at the fire marshal’s discretion. The next likely service disruption is slated to occur along Murphy Lane near Mill Creek Drive and Holyoak Lane near the bowling alley. The road will remain passable but water will be shut off for a few hours.

The excavation for a new 200,000-gallon concrete water tank west of Highway 191 and Rimrock Road has also started. The water tank will sit elevated above the area to provide adequate pressure for future water and fire flow demands.

Sunrise Engineering is overseeing all system upgrades done by Trinity Construction and earlier this month they were closing a loop in the water system with an 8-inch pipe in front of the Spanish Trail Arena. The closed loop will help with flow from Highway 191 down Spanish Valley Drive, including subdivisions near the arena.

The $5.28 million project is being paid for with a $2.7 million loan from the U.S. Department of Agriculture’s Rural Development program, grant funding, and $500,000 from the GWSSA.

Trinity Construction is hiring individuals to join their team on the project.

The company is hiring seasonal workers for the Spanish Valley project and has a variety of positions open ranging from labor to more highly skilled work. Though no previous experience is needed for some of the positions, construction experience is preferred. For more information call project Superintendent Grant Barlow at 435-251-7959.


Copyright 2013 The Times-Independent. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

report abuse...

Express yourself:

We're glad to give readers a forum to express their points of view on issues important to this community. That forum is the “Letters to the Editor.” Letters to the editor may be submitted directly to The Times-Independent through this link and will be published in the print edition of the newspaper. All letters must be the original work of the letter writer – form letters will not be accepted. All letters must include the actual first and last name of the letter writer, the writer’s address, city and state and telephone number. Anonymous letters will not be accepted.

Letters may not exceed 400 words in length, must be regarding issues of general interest to the community, and may not include personal attacks, offensive language, ethnic or racial slurs, or attacks on personal or religious beliefs. Letters should focus on a single issue. Letters that proselytize or focus on theological debates will not be published. During political campaigns, The Times-Independent will not publish letters supporting or opposing any local candidate. Thank you letters are generally not accepted for publication unless the letter has a public purpose. Thank you letters dealing with private matters that compliment or complain about a business or individual will not be published. Nor will letters listing the names of individuals and/or businesses that supported a cause or event. Thank you letters about good Samaritan acts will be considered at the discretion of the newspaper.